As the Lyle Road project moves forward, you will find updates here.
April 2018 - Lyle Road Sales Tax Project passes by 60%
April 2018 - Weatherford City Commission approves engineering contract for Lyle Road design with Myers Engineering
December 2019 - Finalize Utility Relocation Plans
December 2019 - Finalize Roadway Design Plans
January 2020-March 2020 - Application for DEQ Construction Permit
March 2020 - Finalize Right-of-Way Acquisition
June 2020 - Finalize NEPA
June 2020-March 2021 - Utility Relocations
May 2021 - ODOT Bid Letting
June 2021-April 2022 - Construction